PropPin
Caution
  • Possession date passed. The proposed possession date (May 2018) has passed with construction at 60%.

Area guide

What it's like to buy in Mahad (M Cl)

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
SAI ENTERPRISES

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52000008583
Status
Ongoing
Stage
Certificate Signed
Possession
May 2018
Construction
60% complete
Units sold
0 of 0

Similar projects in Mahad (M Cl)

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.