Under construction

ROYAL RESIDENCY

MahaRERA P52000011059High risk

by Royal Enterprises

Survey no 32, Hissa No2A,CTS No 2236, TAKAI, 410203

Official record
Mar 2027
Possession
45.2%
Built
0
Complaints
133
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Mar 2024, now proposed Mar 2027 per the RERA filing.
  • Behind schedule. Possession is due Mar 2027 but construction is only at 45.2%.

Promoter

Builder profile

Builder
Royal Enterprises

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52000011059
Status
Ongoing
Stage
Certificate Signed
Possession
March 2027originally March 2024
Construction
45.2% complete
Units sold
35 of 133

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.