Under construction
ROSEWOOD BUILDING NO. 1
MahaRERA P52000011741High risk
by SVS GROUPS
104/B/1 OF VILLAGE DAHIVALI TARFE NEED, Karjat, 410201
Post your property hereOwn or renting out a unit in ROSEWOOD BUILDING NO. 1? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Karjat come to you.
Mar 2023
Possession
73.1%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Mar 2023) has passed with construction at 73.1%.
- Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Mar 2023 per the RERA filing.
Promoter
Builder profile
SVS GROUPS
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52000011741
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- March 2023originally March 2022
- Construction
- 73.1% complete
- Units sold
- 0 of 0
Similar projects in Karjat
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Meraki Phase 2
KarjatPoss. December 2026
MOHAN NAGAR
KarjatPoss. December 2021
Kalpataru Aria - Phase D
KarjatPoss. December 20262 complaints
Sanskruti Plots, Phase III
KarjatPoss. December 2018
Platinum Co Op Hsg Society
KarjatPoss. December 2030
Kalpataru Aria - Phase C
KarjatPoss. December 2025
Kalpataru Aria - Phase A
KarjatPoss. March 20251 complaint
Globe Fantasiaa Aurelia
KarjatPoss. December 2029
Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.