High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2018, now proposed Oct 2020 per the RERA filing.
  • Possession date passed. The proposed possession date (Oct 2020) has passed with construction at 85.5%.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Oct 2020 per the RERA filing.

Promoter

Builder profile

Builder
SHUBHAM BUILDERS & DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52000012017
Status
Ongoing
Stage
Certificate Signed
Possession
October 2020originally December 2018
Construction
85.5% complete
Units sold
0 of 0

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.