River Residency
MahaRERA P52000012945High risk
1602, 1605 to 1608, Chinchavsli (Shekin), 410203
Post your property hereOwn or renting out a unit in River Residency? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Chinchavsli (Shekin) come to you.
Dec 2027
Possession
47.3%
Built
0
Complaints
0
Units
High risk
- Possession delayed ~8 yrs. Originally promised Apr 2020, now proposed Dec 2027 per the RERA filing.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.
Promoter
Builder profile
Concept Realtors
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52000012945
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2027originally April 2020
- Construction
- 47.3% complete
- Units sold
- 0 of 0
Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.