PropPin
High risk
  • Possession date passed. The proposed possession date (Dec 2022) has passed with construction at 9.1%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2022 per the RERA filing.

Promoter

Builder profile

Builder
AAIJI GROUP

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52000016936
Status
New
Stage
Certificate Signed
Possession
December 2022
Construction
9.1% complete
Units sold
0 of 0

Similar projects in KARANJADE

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.