High risk
  • Possession date passed. The proposed possession date (Mar 2022) has passed with construction at 37.5%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2022 per the RERA filing.

Promoter

Builder profile

Builder
KGN DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52000018905
Status
New
Stage
Certificate Signed
Possession
March 2022
Construction
37.5% complete
Units sold
0 of 0

Similar projects in URAN

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.