PropPin
All RERA projects
🏗️
Under construction

APEX AURA

MahaRERA P52000019129High risk

by APEX BUILDCON

PLOT NO. 11, SECTOR 53, DRONAGIRI, DRONAGIRI, 400702

Official record
Mar 2023
Possession
90.9%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Mar 2023) has passed with construction at 90.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2023 per the RERA filing.

Promoter

Builder profile

Builder
APEX BUILDCON

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52000019129
Status
New
Stage
Certificate Signed
Possession
March 2023
Construction
90.9% complete
Units sold
0 of 0

Similar projects in DRONAGIRI

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.