Under construction
ADINATH NAMAN
MahaRERA P52000023845High risk
by SHREE RIDDHI SIDDHI CONSTRUCTIONS
29, PUSHPAK, VAHAL NODE, 410206
Post your property hereOwn or renting out a unit in ADINATH NAMAN? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in PUSHPAK, VAHAL NODE come to you.
Mar 2024
Possession
90.9%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Mar 2024) has passed with construction at 90.9%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2024 per the RERA filing.
Area guide
What it's like to buy in PUSHPAK, VAHAL NODE
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
SHREE RIDDHI SIDDHI CONSTRUCTIONS
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52000023845
- Status
- New
- Stage
- Certificate Signed
- Possession
- March 2024
- Construction
- 90.9% complete
- Units sold
- 0 of 0
Similar projects in PUSHPAK, VAHAL NODE
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
ADINATH VANDAN
PUSHPAK, VAHAL NODE90.9% builtPoss. May 2024
ADINATH AMBER
PUSHPAK, VAHAL NODE90.9% builtPoss. March 2024
ADINATH ARCHANA
PUSHPAK, VAHAL NODE90.9% builtPoss. December 2024
SHREE SAI
PUSHPAK, VAHAL NODE90.9% builtPoss. April 2024
Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.