PropPin
Caution
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2021 per the RERA filing.

Promoter

Builder profile

Builder
SHREE DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52000024140
Status
New
Stage
Certificate Signed
Possession
June 2021
Construction
100% complete
Units sold
0 of 0

Similar projects in PANVEL

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.