High risk
  • Possession date passed. The proposed possession date (Oct 2021) has passed with construction at 27.3%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Oct 2021 per the RERA filing.

Promoter

Builder profile

Builder
WALMIK RAGHUNATH KHAIRNAR

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52000024658
Status
New
Stage
Certificate Signed
Possession
October 2021
Construction
27.3% complete
Units sold
0 of 0

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.