High risk
  • Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 92%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2026 per the RERA filing.

Promoter

Builder profile

Builder
ARIHANT AASHIYANA PRIVATE LIMITED

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
YOGITA BHANDARKAR

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P52000025041
Status
New
Stage
Certificate Signed
Possession
June 2026originally December 2025
Construction
92% complete
Units sold
86 of 141

Similar projects in Bhisegaon

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.