BRIGHT ENCLAVE
MahaRERA P52000035118High risk
5698, Khopoli, 410203
Post your property hereOwn or renting out a unit in BRIGHT ENCLAVE? List it in seconds β reaches buyers researching this project.Looking to buy or rent here?Post your requirement β sellers & brokers in Khopoli come to you.
Dec 2026
Possession
β
Built
0
Complaints
63
Units
High risk
- Possession delayed ~3 yrs. Originally promised Mar 2024, now proposed Dec 2026 per the RERA filing.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Promoter
Builder profile
BRIGHT BUILDCON
View the promoterβs full developer profile and other projects under the same builder group.
Architect
Design profile
ABHIKALPA ARCHITECTS
Browse other projects associated with this architect to compare design and delivery patterns.
No other projects are linked to this architect yet.
Official RERA facts
- Registration
- P52000035118
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026originally March 2024
- Construction
- β
- Units sold
- 0 of 63
Similar projects in Khopoli
Other MahaRERA-registered projects in the same locality β useful for a like-for-like comparison.
City Of Music Phase III
KhopoliPoss. December 20261 complaint
Ashiyana Infinity
KhopoliPoss. December 2032
Murlidhar Homes Phase 1
KhopoliPoss. December 2030
ALIANA CITY PLAZA PHASE II
Khopoli100% builtPoss. March 2022
Madhav Vaibhav
Khopoli90.9% builtPoss. August 2019
Chishti Apartment
Khopoli90.9% builtPoss. December 2019
NADMOHAN
Khopoli90.9% builtPoss. December 2018
Madhav Ashirwad
Khopoli90.9% builtPoss. January 2021
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.