High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2025, now proposed Dec 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.

Promoter

Builder profile

Builder
CITY AND INDUSTRIAL DEVELOPMENT CORPORATION OF MAHARASHTRA LIMITED

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
Architect Hafeez Contractor

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P52000045446
Status
New
Stage
Certificate Signed
Possession
December 2027originally December 2025
Construction
60.6% complete
Units sold
1313 of 7509

Similar projects in Taloja

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.