All RERA projects
🏗️
Under construction
TUKARAM PALACE
MahaRERA P52000046051High risk
PLOT NO 103 SECTOR 25, PUSHPAK NODE, 410206
Post your property hereOwn or renting out a unit in TUKARAM PALACE? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in PUSHPAK NODE come to you.
Mar 2023
Possession
90.9%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Mar 2023) has passed with construction at 90.9%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2023 per the RERA filing.
Promoter
Builder profile
PREMJI DOSHA VAVIYA
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52000046051
- Status
- New
- Stage
- Certificate Signed
- Possession
- March 2023
- Construction
- 90.9% complete
- Units sold
- 0 of 0
Similar projects in PUSHPAK NODE
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
DHRITI AURA
PUSHPAK NODEPoss. December 2028
THE BELLAGIO
PUSHPAK NODEPoss. December 2027
KRISHNA HILLS
PUSHPAK NODEPoss. December 2029
SIDDHIVINAYAK MANGALAM
PUSHPAK NODEPoss. March 2030
SHREE SADGURU KRUPA
PUSHPAK NODE100% builtPoss. March 2023
SIDDHIVINAYAK DRUSHTI
PUSHPAK NODE100% builtPoss. July 2024
SAI SAMARTH
PUSHPAK NODE100% builtPoss. December 2021
SHREE SADGURU APARTMENT
PUSHPAK NODE100% builtPoss. December 2021
Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.