All RERA projects
ποΈ
Under construction
ARKAN AVENUE
MahaRERA P52000051167High risk
PLOT NO 12G SECTOR 24 TALOJA NAVI MUMBAI 410208, SECTOR 24, 410208
Post your property hereOwn or renting out a unit in ARKAN AVENUE? List it in seconds β reaches buyers researching this project.Looking to buy or rent here?Post your requirement β sellers & brokers in SECTOR 24 come to you.
Dec 2026
Possession
37.3%
Built
0
Complaints
45
Units
High risk
- Behind schedule. Possession is due Dec 2026 but construction is only at 37.3%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Kharghar / PanvelValue
The airport-bet frontier β golf course, hills and heavy new supply.
- Growth drivers:
- Navi Mumbai International Airport, MTHL access, NAINA planning zone.
- Who buys here:
- First-time buyers and investors betting on the airport economy.
PropPin area guide β editorial, not a RERA disclosure.
Promoter
Builder profile
ARKAN DEVELOPERS
View the promoterβs full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52000051167
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026
- Construction
- 37.3% complete
- Units sold
- 9 of 45
Similar projects in SECTOR 24
Other MahaRERA-registered projects in the same locality β useful for a like-for-like comparison.
CENTURY 16
SECTOR 24Poss. December 2029
SHIV BLISS
SECTOR 24100% builtPoss. December 2022
MAHAVIR AAYANSH
SECTOR 24100% builtPoss. December 2021
GANGA HARMONY HOMES
SECTOR 2490.9% builtPoss. December 2021
EKNATH SADAN
SECTOR 2481.8% builtPoss. December 2021
SHIVESH DAMODAR
SECTOR 2447.3% builtPoss. August 2027
BALKRISHNA RESIDENCY
SECTOR 2445.2% builtPoss. December 2023
SAI MOHAN
SECTOR 2418.8% builtPoss. December 2026
Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.