Under construction
CRYSTAL APARTMENT
MahaRERA P52000053146High risk
CTS NO 1648 S NO 62 H NO 8+9 PLOT NO 5 AND 6, CHINCHAVALI SHEKIN, 410203
Post your property hereOwn or renting out a unit in CRYSTAL APARTMENT? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in CHINCHAVALI SHEKIN come to you.
Jun 2027
Possession
44.5%
Built
0
Complaints
0
Units
High risk
- Behind schedule. Possession is due Jun 2027 but construction is only at 44.5%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2027 per the RERA filing.
Promoter
Builder profile
JAVED ISLAM KHAN
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52000053146
- Status
- New
- Stage
- Certificate Signed
- Possession
- June 2027
- Construction
- 44.5% complete
- Units sold
- 0 of 0
Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.