Caution
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.

Promoter

Builder profile

Builder
Mhatre Builders and Developers

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
Vastuyog Architects

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P52000066506
Status
New
Stage
Certificate Signed
Possession
December 2027
Construction
50.9% complete
Units sold
0 of 48