Jun 2033
Possession
45.3%
Built
7
Complaints
207
Units
High risk
  • Possession delayed ~12 yrs. Originally promised Jun 2021, now proposed Jun 2033 per the RERA filing.
  • 7 RERA complaints. 7 complaint records are disclosed against this project on MahaRERA.

Promoter

Builder profile

Builder
Neuleaf Lifespace Developers LLP

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100000181
Status
Ongoing
Stage
Certificate Signed
Possession
June 2033originally June 2021
Construction
45.3% complete
Units sold
120 of 207

Similar projects in Bhugaon

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.