Happiness Hub - Varve

MahaRERA P52100000303High risk

by PARANJAPE SCHEMES (CONSTRUCTION) LTD

Gat No.94/1, 94/2, 96/1, 96/2, 97/1, 97/2, Varve, 412206

Official record
Mar 2025
Possession
88.2%
Built
24
Complaints
0
Units
High risk
  • Possession delayed ~5 yrs. Originally promised Mar 2020, now proposed Mar 2025 per the RERA filing.
  • 24 RERA complaints. 24 complaint records are disclosed against this project on MahaRERA.
  • Possession date passed. The proposed possession date (Mar 2025) has passed with construction at 88.2%.

Promoter

Builder profile

Builder
PARANJAPE SCHEMES (CONSTRUCTION) LTD

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100000303
Status
Ongoing
Stage
Certificate Signed
Possession
March 2025originally March 2020
Construction
88.2% complete
Units sold
0 of 0

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.