All RERA projects
🏗️
Under construction
Green park
MahaRERA P52100000501High risk
by Anishka Developers Pvt. Ltd.
25/2/2A, Kondhwa Bk, 411048
Post your property hereOwn or renting out a unit in Green park? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Kondhwa Bk come to you.
Jun 2024
Possession
98.2%
Built
0
Complaints
0
Units
High risk
- Possession delayed ~2 yrs. Originally promised Dec 2022, now proposed Jun 2024 per the RERA filing.
- Possession date passed. The proposed possession date (Jun 2024) has passed with construction at 98.2%.
Promoter
Builder profile
Anishka Developers Pvt. Ltd.
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P52100000501
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- June 2024originally December 2022
- Construction
- 98.2% complete
- Units sold
- 0 of 0
Similar projects in Kondhwa Bk
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Pardeshi-Darawade Height
Kondhwa Bk80.9% builtPoss. December 2024
Redision Royal
Kondhwa Bk13.6% builtPoss. November 2033
AUDUMBAR RESIDENCY
Kondhwa Bk9.1% builtPoss. December 2026
Elite Sparsh
Kondhwa Bk4.5% builtPoss. December 2028
GAGAN MEHER
Kondhwa Bk0% builtPoss. December 2024
Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.