PropPin
High risk
  • Litigation pending (1). MahaRERA's litigation disclosure lists 1 pending case against this project.
  • Possession delayed ~2 yrs. Originally promised Jun 2019, now proposed Dec 2020 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2020) has passed with construction at 81.7%.

Promoter

Builder profile

Builder
SIA Developers

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100001456
Status
Ongoing
Stage
Certificate Signed
Possession
December 2020originally June 2019
Construction
81.7% complete
Units sold
0 of 0