Under construction

Renuka Gulmohar Phase II

MahaRERA P52100001835High risk

SNO 33 P 36 P CTS NO 5861 P AT PIMPRI WAGHERE,HAVELI,PUNE, Haveli, 411018

Official record
Dec 2023
Possession
82.1%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2023) has passed with construction at 82.1%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2023 per the RERA filing.

Official RERA facts

Registration
P52100001835
Status
Ongoing
Stage
Certificate Signed
Possession
December 2023
Construction
82.1% complete
Units sold
0 of 0