PropPin
High risk
  • Possession date passed. The proposed possession date (Sept 2018) has passed with construction at 82.7%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2018 per the RERA filing.
Thane (Ghodbunder belt)Mid-income

A full city of its own β€” lakes, malls and township-scale supply along Ghodbunder Road.

Growth drivers:
Metro 4/5 corridors, big-brand townships, spillover from Mumbai pricing.
Who buys here:
Families upgrading to space and amenities without island-city prices.

PropPin area guide β€” editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
ADITYA ASSOCIATES

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100002988
Status
Ongoing
Stage
Certificate Signed
Possession
September 2018
Construction
82.7% complete
Units sold
0 of 0

Similar projects in Talegaon Dabhade (R)

Other MahaRERA-registered projects in the same locality β€” useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.