33 keshav kunj
MahaRERA P52100003364High risk
S.NO.33/3B/1A, 33/3B/1B, 33/3B/2 33/3B/3B, 333B/4, 33/3B/5,33/3B3A, Mundhawa, Mundhawa, 411036
Post your property hereOwn or renting out a unit in 33 keshav kunj? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Mundhawa come to you.
Dec 2025
Possession
95.4%
Built
0
Complaints
0
Units
High risk
- Possession delayed ~6 yrs. Originally promised Sept 2019, now proposed Dec 2025 per the RERA filing.
- Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 95.4%.
Promoter
Builder profile
CRYSTAL PROPERTIES
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100003364
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2025originally September 2019
- Construction
- 95.4% complete
- Units sold
- 0 of 0
Similar projects in Mundhawa
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Envisage
MundhawaPoss. September 2029
UNI 89 WING C
MundhawaPoss. December 2029
EPITOME BUSINESS CENTER
MundhawaPoss. June 2029
LIORA
MundhawaPoss. March 2029
Global Riverfront- Phase 1
MundhawaPoss. December 2030
57 Avenue
MundhawaPoss. December 2032
Godrej Aqua Vista
MundhawaPoss. March 20322 complaints
SUN GARNET
MundhawaPoss. December 2030
Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.