PropPin
🏗️
Under construction

SHREE RESIDENCY PHASE A

MahaRERA P52100004908High risk

by UK CONSTRUCTION

GAT NO 148 AND GAT NO 142, Haveli, 412202

Official record
Oct 2020
Possession
80%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Apr 2019, now proposed Oct 2020 per the RERA filing.
  • Possession date passed. The proposed possession date (Oct 2020) has passed with construction at 80%.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Oct 2020 per the RERA filing.

Promoter

Builder profile

Builder
UK CONSTRUCTION

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100004908
Status
Ongoing
Stage
Certificate Signed
Possession
October 2020originally April 2019
Construction
80% complete
Units sold
0 of 0

Similar projects in Haveli

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.