High risk
  • Possession date passed. The proposed possession date (Jun 2019) has passed with construction at 63.2%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2019 per the RERA filing.

Promoter

Builder profile

Builder
S S ASSOCIATES

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100004953
Status
Ongoing
Stage
Certificate Signed
Possession
June 2019originally June 2018
Construction
63.2% complete
Units sold
0 of 0