  • Possession delayed ~4 yrs. Originally promised Jun 2022, now proposed Jun 2026 per the RERA filing.
  • 25 RERA complaints. 25 complaint records are disclosed against this project on MahaRERA.
  • Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 95.5%.

Promoter

Builder profile

Builder
Vedant Landmarks

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100005525
Status
Ongoing
Stage
Certificate Signed
Possession
June 2026originally June 2022
Construction
95.5% complete
Units sold
0 of 0

Similar projects in MOHAMMADWADI

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.