PropPin
High risk
  • Possession date passed. The proposed possession date (Dec 2018) has passed with construction at 75%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2018 per the RERA filing.

Promoter

Builder profile

Builder
P.S.CONSTRUCTIONS

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100005848
Status
Ongoing
Stage
Certificate Signed
Possession
December 2018
Construction
75% complete
Units sold
0 of 0

Similar projects in Hadapsar

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.