All RERA projects
🏗️
Under construction
PAVILLION RESIDENCY
MahaRERA P52100006615High risk
1/4/2, Mahalunge, 411045
Post your property hereOwn or renting out a unit in PAVILLION RESIDENCY? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Mahalunge come to you.
Dec 2018
Possession
63.6%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Dec 2018) has passed with construction at 63.6%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2018 per the RERA filing.
Promoter
Builder profile
APEX DEVELOPERS
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100006615
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2018
- Construction
- 63.6% complete
- Units sold
- 0 of 0
Similar projects in Mahalunge
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Dahlia
MahalungePoss. June 2029
Raheja Vistas - T1 & T2
MahalungePoss. July 2031
Raheja Vistas - T6 & T7
MahalungePoss. July 2031
Raheja Vistas - T4
MahalungePoss. July 2031
Mahalunge Riviera
Mahalunge100% builtPoss. December 2020
Aldea Espanola Phase VII
Mahalunge90.9% builtPoss. December 2028
SHIVAM GREENCOURT
Mahalunge90.9% builtPoss. October 2021
SWASTIK MUHURTAM
Mahalunge90.9% builtPoss. December 2017
Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.