High risk
- Possession date passed. The proposed possession date (Jun 2022) has passed with construction at 79.5%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2022 per the RERA filing.
Area guide
What it's like to buy in Pisoli
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
NAYAN BUILDCON
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100006878
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- June 2022originally June 2021
- Construction
- 79.5% complete
- Units sold
- 0 of 0
Similar projects in Pisoli
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Prime Vista
PisoliPoss. December 2029
Advika Phase IV-C
PisoliPoss. December 2030
Prime Vista Row Houses
PisoliPoss. December 2029
EMERALD GREEN
PisoliPoss. August 2028
GAGAN LAWISH PHASE 2
Pisoli100% builtPoss. December 2020
ARV Imperia C, D and E Building
Pisoli100% builtPoss. December 201828 complaints
ATUR VALLY VISTA WING B
Pisoli95% builtPoss. December 2017
BROOKEFIELD WILLOWS
Pisoli90.9% builtPoss. December 20191 complaint