PropPin
Caution
  • Possession delayed ~2 yrs. Originally promised Apr 2019, now proposed Oct 2020 per the RERA filing.

Promoter

Builder profile

Builder
Milestone Developers

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100006981
Status
Ongoing
Stage
Certificate Signed
Possession
October 2020originally April 2019
Construction
100% complete
Units sold
0 of 0

Similar projects in Nanekarwadi (CT)

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.