Sukhwani Gracia Phase-3 C, Wing

MahaRERA P52100007982High risk

by Prime properties

Survey no-221/2/a/1, 222/c/1, 222/c/2, 222/c/3, 222/c/4, 222/c/5., Mulshi, 411021

Official record
Dec 2027
Possession
90.9%
Built
4
Complaints
0
Units
High risk
  • Possession delayed ~7 yrs. Originally promised Apr 2021, now proposed Dec 2027 per the RERA filing.

Promoter

Builder profile

Builder
Prime properties

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100007982
Status
Ongoing
Stage
Certificate Signed
Possession
December 2027originally April 2021
Construction
90.9% complete
Units sold
0 of 0

Similar projects in Mulshi

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.