PropPin
High risk
  • Possession date passed. The proposed possession date (Nov 2018) has passed with construction at 90.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Nov 2018 per the RERA filing.

Promoter

Builder profile

Builder
GURUKRUPA DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100008282
Status
Ongoing
Stage
Certificate Signed
Possession
November 2018
Construction
90.9% complete
Units sold
0 of 0