All RERA projects
🏗️
Under construction
KOHINOOR BEGONIA PHASE III
MahaRERA P52100008679High risk
SURVEY NO 51 HISSA NO2 SUB DIVISION 2, varale phata, 410507
Post your property hereOwn or renting out a unit in KOHINOOR BEGONIA PHASE III? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in varale phata come to you.
Dec 2021
Possession
90.9%
Built
1
Complaints
0
Units
High risk
- Possession delayed ~2 yrs. Originally promised Dec 2019, now proposed Dec 2021 per the RERA filing.
- Possession date passed. The proposed possession date (Dec 2021) has passed with construction at 90.9%.
Promoter
Builder profile
KOHINOOR ASSOCIATES
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100008679
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2021originally December 2019
- Construction
- 90.9% complete
- Units sold
- 0 of 0