Under construction
BIRDS COUNTY
MahaRERA P52100010148High risk
SURVEY NUMBER 129, Wakad, 411057
Post your property hereOwn or renting out a unit in BIRDS COUNTY? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Wakad come to you.
Dec 2017
Possession
90.9%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Dec 2017) has passed with construction at 90.9%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2017 per the RERA filing.
Promoter
Builder profile
D P K ASSOCIATES
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P52100010148
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2017
- Construction
- 90.9% complete
- Units sold
- 0 of 0
Similar projects in Wakad
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Rajveer Garima Phase 2
WakadPoss. December 2031
The Embercrest
WakadPoss. December 2031
LUXTON
WakadPoss. June 2030
Millefiori
WakadPoss. June 2030
RUNAA SAUKHYAM
WakadPoss. March 2029
Highness
WakadPoss. December 2032
Prissa Pratham
WakadPoss. December 2030
Siddhi's Sapphire Homes
WakadPoss. December 2027
Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.