Phase I - Buildings A, A1, P and S,T,U Combined wing
MahaRERA P52100010202High risk
Gat No 4523 4524 4525, Chakan (CT), 410501
Post your property hereOwn or renting out a unit in Phase I - Buildings A, A1, P and S,T,U Combined wing? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Chakan (CT) come to you.
Dec 2030
Possession
90.5%
Built
1
Complaints
245
Units
High risk
- Possession delayed ~9 yrs. Originally promised Dec 2021, now proposed Dec 2030 per the RERA filing.
Promoter
Builder profile
Shree Sai Associates
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100010202
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2030originally December 2021
- Construction
- 90.5% complete
- Units sold
- 113 of 245
Similar projects in Chakan (CT)
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
PRASANNA I SQUARE
Chakan (CT)90.9% builtPoss. September 2021
Vaishnavi Park
Chakan (CT)90.9% builtPoss. December 2021
TIARA MEADOW PHASE I
Chakan (CT)90% builtPoss. July 2018
VASTU FOREST NEST
Chakan (CT)89.1% builtPoss. March 20187 complaints
SHRIRAM REALITY
Chakan (CT)81.8% builtPoss. September 2020
EKAAKSHARA HEIGHTS
Chakan (CT)56.4% builtPoss. September 2020
Siddhi Homes
Chakan (CT)47.3% builtPoss. May 2022
Atharva Patson Phinix PH II
Chakan (CT)7.9% builtPoss. July 2023
Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.