Under construction
Greenaria Building B
MahaRERA P52100016582High risk
131/4/1, Hadapsar, 411028
Post your property hereOwn or renting out a unit in Greenaria Building B? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Hadapsar come to you.
Oct 2022
Possession
90.9%
Built
1
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Oct 2022) has passed with construction at 90.9%.
- Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Oct 2022 per the RERA filing.
Area guide
What it's like to buy in Hadapsar
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
RAVIRAJ CONSTRUCTIONS
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100016582
- Status
- New
- Stage
- Certificate Signed
- Possession
- October 2022
- Construction
- 90.9% complete
- Units sold
- 0 of 0
Similar projects in Hadapsar
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
AASTHA HOUSING
HadapsarPoss. September 2029
Niwaas
HadapsarPoss. May 202710 complaints
Euphoric Blossom
HadapsarPoss. April 2030
SAIRANG RESIDENCY
HadapsarPoss. May 2028
54 Flores Drive Phase 2
HadapsarPoss. June 2031
Kumar Parc Residences - B1
HadapsarPoss. October 2030
54 Flores Drive Phase 1
HadapsarPoss. June 2029
AVINEA PHASE 2
HadapsarPoss. December 2029
Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.