Under construction
WEST AVENUE
MahaRERA P52100016725High risk
S.NO2 H.NO 2B,3A,3B , CTS NO 2561 PART , AUNDH, PANDI BHIMSEN KALAMANDIR, 411067
Post your property hereOwn or renting out a unit in WEST AVENUE? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in PANDI BHIMSEN KALAMANDIR come to you.
Aug 2023
Possession
38%
Built
0
Complaints
184
Units
High risk
- Possession date passed. The proposed possession date (Aug 2023) has passed with construction at 38%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Aug 2023 per the RERA filing.
Area guide
What it's like to buy in PANDI BHIMSEN KALAMANDIR
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
RAINBOW CONSTRUCTIONS
View the promoter’s full developer profile and other projects under the same builder group.
Architect
Design profile
Hirak - Shah
Browse other projects associated with this architect to compare design and delivery patterns.
Official RERA facts
- Registration
- P52100016725
- Status
- New
- Stage
- Certificate Signed
- Possession
- August 2023originally February 2023
- Construction
- 38% complete
- Units sold
- 165 of 184
Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.