High risk
  • Mortgaged to a lender (₹4.7 Cr). MahaRERA's financial encumbrance declaration shows this project has ₹4.7 Cr secured against a lender — a lender's claim can outrank a buyer's if the promoter defaults.
  • Possession delayed ~3 yrs. Originally promised Dec 2023, now proposed Dec 2026 per the RERA filing.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2026 per the RERA filing.

Promoter

Builder profile

Builder
MAITRI DEVELOPERS AND BUILDERS

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
MILIND PANCHAL

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P52100016857
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2023
Construction
64.7% complete
Units sold
38 of 47

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.