Under construction

MADHUVRUNDA CO-OPERATIVE HOUSING SOCIETY

MahaRERA P52100018201Caution

by Aakar Constructions

109/1 , CTS NO 75, ERANDWANE, 411004

Official record
Feb 2022
Possession
64.5%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Feb 2022) has passed with construction at 64.5%.

Area guide

What it's like to buy in ERANDWANE

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Aakar Constructions

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100018201
Status
New
Stage
Certificate Signed
Possession
February 2022
Construction
64.5% complete
Units sold
0 of 0

Similar projects in ERANDWANE

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.