PropPin
High risk
  • Possession date passed. The proposed possession date (May 2019) has passed with construction at 55.5%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due May 2019 per the RERA filing.

Promoter

Builder profile

Builder
Arun Pitamber Sheth

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100018361
Status
New
Stage
Certificate Signed
Possession
May 2019
Construction
55.5% complete
Units sold
0 of 0

Similar projects in PISOLI

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.