High risk
  • Possession delayed ~3 yrs. Originally promised Jan 2024, now proposed Sept 2026 per the RERA filing.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Sept 2026 per the RERA filing.

Promoter

Builder profile

Builder
Rose Dream Developers

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100019495
Status
New
Stage
Certificate Signed
Possession
September 2026originally January 2024
Construction
63.5% complete
Units sold
0 of 0

Similar projects in Khed

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.