PropPin
High risk
  • Possession date passed. The proposed possession date (Dec 2024) has passed with construction at 18.5%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2024 per the RERA filing.

Promoter

Builder profile

Builder
Prasun Associates

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100021383
Status
New
Stage
Certificate Signed
Possession
December 2024
Construction
18.5% complete
Units sold
0 of 0

Similar projects in Kharadi

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.