PropPin
High risk
  • Possession date passed. The proposed possession date (Dec 2019) has passed with construction at 45.2%.

Promoter

Builder profile

Builder
NITIN DWARKADAS NYATI

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100021443
Status
New
Stage
Certificate Signed
Possession
December 2019
Construction
45.2% complete
Units sold
0 of 0

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.