CASALINO TOWERS PHASE II
MahaRERA P52100023594High risk
by SAI SIDDHI PROMOTERS AND BUILDERS
13 PART, HANDEWADI, 412308
Post your property hereOwn or renting out a unit in CASALINO TOWERS PHASE II? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in HANDEWADI come to you.
Dec 2023
Possession
9.1%
Built
1
Complaints
112
Units
High risk
- Possession date passed. The proposed possession date (Dec 2023) has passed with construction at 9.1%.
- Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2023 per the RERA filing.
Promoter
Builder profile
SAI SIDDHI PROMOTERS AND BUILDERS
View the promoter’s full developer profile and other projects under the same builder group.
Architect
Design profile
SHAILESH PRAKASH DANDANE
Browse other projects associated with this architect to compare design and delivery patterns.
No other projects are linked to this architect yet.
Official RERA facts
- Registration
- P52100023594
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2023
- Construction
- 9.1% complete
- Units sold
- 95 of 112
Similar projects in HANDEWADI
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
SILVER STONE
HANDEWADI79.2% builtPoss. June 20252 complaints
GOLDEN NEST B building
HANDEWADI60.9% builtPoss. December 2028
KUMAR PEBBLE PARK KHUSHI 2- D2
HANDEWADI49.1% builtPoss. April 2024
GANRAJ SWAPNAPURTI PHASE II
HANDEWADI28.6% builtPoss. September 2023
CASALINO TOWERS - PHASE 1
HANDEWADI18.2% builtPoss. December 2023
Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.