High risk
  • Possession delayed ~2 yrs. Originally promised Jul 2024, now proposed Jul 2026 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jul 2026 per the RERA filing.

Promoter

Builder profile

Builder
Anandtara Properties

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
Mr Vikas Achalkar

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P52100024639
Status
Ongoing
Stage
Certificate Signed
Possession
July 2026originally July 2024
Construction
64% complete
Units sold
14 of 59