PropPin
All RERA projects
🏗️
Under construction

ESPACIO - WING C D AND E/MHADA

MahaRERA P52100025099High risk

by KNIGHT WEST REALTY LLP

S. NO. 38, H. NO. 8 AT BALEWADI, BALEWADI, 411045

Official record
Dec 2025
Possession
78.8%
Built
0
Complaints
126
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 78.8%.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Dec 2025 per the RERA filing.

Promoter

Builder profile

Builder
KNIGHT WEST REALTY LLP

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
Malwadkar Architects

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P52100025099
Status
New
Stage
Certificate Signed
Possession
December 2025
Construction
78.8% complete
Units sold
119 of 126

Similar projects in BALEWADI

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.