PropPin
High risk
  • Possession date passed. The proposed possession date (Dec 2022) has passed with construction at 39.1%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2022 per the RERA filing.

Promoter

Builder profile

Builder
Vinayak Pandharinath Bhongale

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100025230
Status
New
Stage
Certificate Signed
Possession
December 2022
Construction
39.1% complete
Units sold
0 of 0