PropPin
High risk
  • Possession date passed. The proposed possession date (Jan 2026) has passed with construction at 46.4%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jan 2026 per the RERA filing.

Area guide

What it's like to buy in Chikhali

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
VIJAY CONSTRUCTION NEXT

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100025794
Status
New
Stage
Certificate Signed
Possession
January 2026
Construction
46.4% complete
Units sold
0 of 0

Similar projects in Chikhali

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.